AP-Assisted one of Romania’s most important EPC contractors, covering with its projects entire energy chain

Assisted one of Romania’s most important EPC contractors, covering with its projects entire energy chain – from energy generation to transmission, distribution and supply in an ad-hoc arbitration case and subsequent litigation cases – maintaining the favorable arbitral decision – filed for a claim of EUR 1 million arising in connection with the performance of a public works FIDIC contract with a total value of EUR 10.5 million.